How it works
Net time = available time − downtime. The result is a target, not a demonstrated machine capability. Yield loss, parallel stations and changeover variability must be modeled separately.
Worked example
A 480-minute shift with 60 minutes of planned downtime and 120 units to make needs an average cycle time of 3.5 minutes per unit, or 17.1 units per productive hour.
How the required cycle time changes with production time available
Other inputs keep their starting values: Units required: 120; Planned downtime (minutes): 60. Examples only, not recommendations.
| Production time available (minutes) | Required cycle time (minutes per unit) |
|---|---|
| 240 | 1.5 |
| 480 | 3.5 |
| 960 | 7.5 |